|
Roberts
was contracted by MK-Ferguson, Weldon Springs, Mo.,
and Jacobs Engineering, St. Louis, Mo., to perform lake
sediment sampling in lake number 34 and lake number
35 in the August A. Busch Wildlife Area, located near
Weldon Spring, Mo. The possibility existed that some
radioactive material may have reached the lakes due
to runoff from the nearby Department of Energy's (DOE)
former weapons plant site, The Weldon Springs Plant,
located in St. Charles, Mo.
The DOE
site has a history of radioactive contamination dating
back to World War II. Radioactive materials related
to the infamous "Manhattan Project," the name given
to the development of the atomic bombs dropped on Hiroshima
and Nagasaki, were processed and disposed of at the
St. Charles DOE site. The Weldon Springs Plant was also
one of the largest producers of trinitrotoluene (TNT)
during the war, which contributed to a large degree
of contamination on the several-hundred-acre site. The
plant site is now in the final phase of clean-up and
restoration.
The strict
sampling specifications required for this job called
for a series of borings, 314 total, to collect lake
sediments and to penetrate a minimum of one foot into
the natural soil beneath the sediment with at least
a 95 percent recovery rate. Each boring was required
to be located within one meter of the proposed sample
location determined by a Global Positioning System (GPS)
receiver with "real time" centimeter accuracy. The GPS
consists of 24 Earth-orbiting satellites that allow
anyone with a GPS receiver to determine precise latitude,
longitude or altitude anywhere on the planet. GPS receivers
measure the amount of time it takes a signal to travel
from the satellite to the receiver using the speed of
light as a reference. Due to the expense of GPS equipment
and the cost involved to train or hire someone to operate
the receiver, Roberts decided to subcontract for a GPS
surveyor. They chose Kuhlman Design Group, a surveying
and engineering company located in St. Charles, Mo.,
that owned a Trimble Pathfinder GPS receiver that met
the specifications required.
Once awarded
the contract, Roberts had 30 days to acquire and construct
the equipment needed to access the lakes and collect
the samples. Roberts purchased a rebuilt Mobile B-24
skid mounted rig and two used 24-foot pontoon boats
for this project. They also modified a CME Continuous
Soil Sampler; a tool specially designed to collect continuous
soil samples in conjunction with hollow-stem auger drilling.
Roberts modified this piece of equipment by extending
the cutting shoes and fitting them with shop-made sediment
retainers (designed by Roberts), creating finger-like
catchers for the softer soil. Roberts also had a 10-foot
sample barrel constructed. They purchased a few hundred
feet of clear, polyethylene sample liner material and
cut it to their specifications.
"We fabricated
a few things we thought might work and, in the end,
they worked quite well and made the job go more quickly
and smoothly," said Charley Roberts, president and owner
of Roberts Environmental Drilling, Inc.
Prior to
commencing site work, Roberts mounted two additional
pontoons for supplemental floatation under the pontoon
boat designated for the drill rig. The contract required
that Roberts be able to access areas in the lakes from
14 inches deep up to 20 feet deep. They cut a hole to
drill through in the deck of the pontoon and mounted
four removable spuds, or anchors, on each corner to
secure the boat's location during drilling. The sampling
crew used the other boat to process the sediment samples
and transport personnel back to shore.
Although
there was less sediment in the lakes than Roberts expected,
it took time for them to set up at each location and
push the sampler into new soil. The drill crew and GPS
surveyor developed a navigation system for the drill-rig
boat to ensure the boat stopped within three feet of
the pre-established sampling locations. This was especially
challenging during windy days.
Safety was
of the utmost importance to Roberts during this project.
Safety standards were strictly enforced, including extensive
operator training, providing radiation education and
training, and employing a high ratio of safety workers
to operators to oversee all aspects of the project.
Roberts
sampled 117 borings in lake number 34 and 197 borings
in lake number 35. They completed the project in just
less than two months, 30 days ahead of schedule and
$38,000 under budget. In the end, no radiation levels
were found that were above background, or naturally
occurring, levels.
Upon completion
of the project, MK-Ferguson provided a catered lunch
for all personnel involved in the project and presented
Roberts with a Certificate of Outstanding Performance
from MK-Ferguson, Jacobs Engineering and the DOE.
"It's a
great feeling to finish a job and exceed everyone's
expectations," Roberts said.
Roberts
Environmental Drilling, Inc. has been an NDA member
for six years. It has been in business since 1992 and
has 16 employees, seven drill rigs and several Geoprobes.
Resources:
Contracted by: MK-Ferguson, Jacobs Engineering
Location: Weldon Spring, MO
Drilling Contractor: Roberts Environmental Drilling
Tel: 618-476-7334
Fax: 618-476-3619
E-mail: redidrill@aol.com
|